Quincy Compressor Startup Checklist
|
| Customer & Unit Info |
| Customer: | S/O No.: |
| Unit Model: | Serial #: |
| Lube Type:
Quin-Syn Plus
Quin-Syn PG
Quin-Syn FG
Other: |
|
| Startup Checklist |
| Review instruction manual |
| Removing shipping bolts per instruction book |
| Check electrical connections, unit grounded, protected against short circuits |
| Check starter to control panel interconnect (external starter) |
| Check control panel transformer connections & jumpers |
| Check & verify setting of motor overload relay and fan circuit breaker |
| Check all control panel electrical connections for tightness |
| Check all shut down switch settings and adjust for specifications |
| Check to ensure all safety Shields are in place |
| Check fluid drain plugs for tightness and leakage |
| Check fluid level in tank and top up if necessary (DO NOT MIX FLUIDS) |
| Pour 1 qt of fluid into inlet (DO NOT MIX FLUIDS) |
| Check for correct condensate drain line installation (open drain) |
| Check cooling water connections (solenoid, strainer) |
| Check air system piping (receiver, condensate collection) |
| Check room for proper ventilation (see product data) |
| Turn on power |
| Jog the compressor and verify correct drive motor and cooling fan motor rotation |
| Start unit and run unloaded for a few minutes |
| Stop unit & recheck fluid level |
| Repair any oil, air or water leaks as required |
| Restart and load compressor |
| Adjust pressure switch for customer conditions |
| Adjust cooling water flows |
| Allow unit to warm, measure and record all temperature, pressures |
| Instruct customer on unit operation |
| Instruct customer on preventive main. sched. (Daily, 4000 hrs, 8000 hrs, etc.) |
Job Notes:
|
| |
| Customer Signature: | Date: |
| Technician Signature: | Date: |